Import Schedule Status

Prerequisites

  • The schedule tool was used to create or maintain the budget baseline in EVMax.
  • The current status date in the schedule tool matches the current period ending date in EVMax.
  • You have entered the applicable activity status for the current reporting period in your schedule tool. This includes the actual start date when the activity begins, actual finish date when the activity completes, and physical percent complete. The schedule activity physical percent complete is the basis to calculate the work package percent complete in EVMax.
  • Close the schedule tool. This ensures the current schedule status is saved in the schedule tool project before you import the data into EVMax.

Tip:

Should you identify an error in the earned value data, you can clear the current period earned value data (see Remove Current Earned Values), fix the errors in the schedule tool, and then import the schedule status again.